Passive First provided a supply and install quotation at the invitation of the electrical contractor of three residential towers. This was to fire stop all the electrical risers in the towers which covered over 50 floors.

Given the enormity of the project, Passive First decided to move away from using conventional fire pillow or fire mortar systems, instead opting to install an intubatt fire stop system.

Passive First went ahead installing the intubatt fire stop system, complete with fire mastic and penetration wrapping of cables and cable trays to over 205 floor riser penetrations and over 20 wall penetrations.

Each completed fire stopping system was labeled and photographed to be included in an itemised Passive First certification form that was used as a part of the final certification process with the builder.